Seguin

Summary

A new 94-foot clarifier adds redundant treatment capacity and replaces pumps at the end of their life, positioning the city for a future water plant replacement. It's a $19.5 million investment funded through certificates of obligation.

At a glance

Total mentions
1
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Oct 20, 2026.

Impact analysis

💰Financial impact

$19.5 million, paid for with certificates of obligation.

✅Who benefits

Every resident who depends on reliable city water, especially as growth continues north of I-10.